The domestic maximum power high-speed natural gas compressor set completed no-load commissioning

On October 23, the domestically-produced high-speed high-speed natural gas compressor RTY3360 successfully completed the no-load commissioning at the Shapingchang booster station in the Liangping work area of ​​the Southwest Oil and Gas Field.

The compressor units in June last year the factory lifting to the scene, lifting into place in December, in May of this year to complete the installation, 9 months late intermediate acceptance. In more than one month, after the rectification of the problem, the purging, replacement, boosting, leak testing, and joint debugging of the unit and supporting pipelines, the unit successfully completed no-load and small-cycle debugging of the unit, creating a good test for the unit's loading and running. condition.