How long will it take to get a house?

Before the renovation, everyone's concern is how long the renovation will take, because they all want to rush to live in a new house, but sometimes due to various reasons, will always procrastinate for a long time, today Xiaobian will calculate the renovation for everyone Every specific time, I hope you understand and avoid unnecessary trouble!

First, it takes time before starting

1. At least 10 days before the start of the project: Make a design plan; select the decoration company, put forward the decoration content and requirements; measure the relevant data in the field and draw detailed drawings; communicate with the designer thoroughly to determine the final plan.

2. At least 5 days before the start of work: look at the budget to sign the contract; determine the materials to be used; make an initial budget for the cost of home improvement; compare it with the budget of the home improvement company; sign the decoration contract.

3. At least 2 days before construction: Prepare before entering the fair; Contact with the property department to complete necessary procedures; Greeting with neighbors; Entry of door and window materials and auxiliary materials; Handing the key to the construction side;

Second, time-consuming decoration

1. Structure Dismantling: 1-2 days

Before the house decoration, the structure is generally demolition and reform according to the design scheme. The houses of small and medium-sized houses generally take 1-2 days. If your family does not have this item, you can subtract this time.

2, hydropower reform: 5-10 days

The hydropower transformation is the slotting, wiring, acceptance, etc., depending on the complexity of the project, generally takes 5-10 hours, sometimes even longer.

3, mud tile project: about 15 days

The tile project includes items such as kitchen and toilets, waterproofing, ceramic tiles, and the like, and the time required varies depending on the area of ​​the tiles to be tiled. Usually about 15 days, if the waterproof does not pass the acceptance, the time may be longer.

4, woodworking engineering: about 10 days

Carpentry works include ceilings, floors, wooden walls, and furniture production. It may take up to 20 days for a long period of time. The short time may be due to the use of finished furniture and no woodwork.

5, paint project: about 10 days

The paint works mainly include wall surfaces, ceiling paints, wallpapers, etc. Since the paint usually needs to be putty before it can be used for brushing primers and top coats, and sometimes it needs to be brushed several times, so the duration of the work needs about 10 days.

Third, the construction finishing

1, installation and closing: about 5 days

The final stage of installation includes the installation of various sanitary wares, the installation of floors, the installation of cabinets, etc. These installations can be performed several times a day because there is no conflict and influence. Therefore, if the products enter the market in a timely manner, they will be properly installed and installed. It can be done in days.

The above is only taking the size of the most common house type as an example. After all, a 100-level house decoration may take about 50 days.

Tips: More practical decoration knowledge, real scene with the shoot, please pay attention to the palm of this site (micro signal: mall_jia).

Decoration construction knowledge

Aluminum Brazing Sheet

Brazing Sheet,3003 Aluminum Sheet,Clad Aluminum Sheet,Aluminium Brazing Sheet

Trumony Aluminum Limited , https://www.trumonyalu.com